A five mile stretch of temporary narrow lanes have been removed between junctions 18 and 20 on the M62 marking the start of a phased opening of the North West’s first smart motorway scheme.

Extra lanes will also be opened on the M62 before the Christmas getaway, increasing capacity on the stretch of motorway between Greater Manchester and Yorkshire by a third say the Highways Agency.

Overnight closures will continue to take place between junctions 18 and 20 on the M62 to carry out resurfacing work and to commission the new smart motorway technology.

The closures will be in place between 10pm and 6am, Sunday to Thursday, and between 9pm and 10am on Friday and Saturday nights. Overnight closures will also continue on sections of the M60 for major construction work on the smart motorway.

The scheme is Highways England’s most complex smart motorway project, affecting the second busiest motorway in the country and covering 13 junctions – an average of one junction every 1.4 miles.

The full scheme stretches between junction 8 of the M60 near Sale and junction 20 of the M62 near Rochdale. The next stage of the phased opening will see the removal of the temporary narrow lanes between junctions 8 and 10 on the M60 later in the autumn.

The new technology will be tested to ensure the 100 traffic sensors which have been installed along the 17-mile route are working effectively, before the new electronic variable speed limit signs are switched on from junctions 8 to 10 on the M60 and junctions 18 to 20 on the M62 by the end of the year.

The temporary narrow lanes are due to be removed between junctions 15 and 18 on the M60 in early 2018, and from the final section of roadworks – on a 5 mile stretch of the M60 between junctions 10 and 15 – in spring 2018. The new variable speed limit signs are due to be switched on between junctions 10 and 18 by summer 2018.