Highways England is opening a permanent fourth lane in each direction between junctions 18 and 20 of the M62 over the next two evenings.

Roadworks will be removed from the eastbound carriageway tonight and from the westbound carriageway tomorrow night.

New electronic signs will also be switched on along this section of the M62 as well as on the M60 between junctions 8 and 10 near the Trafford Centre, providing drivers with journey time updates and details on incidents.

The opening of ten miles of extra lanes on the M62 are among almost 400 miles of roadworks across England being lifted or completed by Highways England in time for the Christmas getaway.

Variable speed limits will be introduced on the M62 (junctions 18 to 20) and the M60 (junctions 8 to 10) in early 2018 which will automatically change in response to the flow of traffic.

The speed limit will remain at 50mph while the new technology is being fine-tuned.

Construction work will continue between junctions 10 and 18 on the M60 in 2018 to complete the installation of over 350 electronic signs, over 100 traffic sensors and 50 CCTV cameras.

Resurfacing work will also take place along the entire smart motorway route using overnight carriageway closures. The project is due to be completed by summer 2018.

The scheme is Highways England’s most complex smart motorway project, affecting the second busiest motorway in the country and covering 13 junctions – an average of one junction every 1.4 miles.

The full scheme stretches 17 miles between junction 8 of the M60 near Sale and junction 20 of the M62 near Rochdale.