Railway passengers in Greater Manchester move one step closer to faster, more frequent, more reliable trains after major railway upgrades were completed on time between Manchester Victoria, Rochdale and Stalybridge.

Work took place from Saturday 31 July until Sunday 15 August to completely reconstruct railway bridges on Dantzic Street and Queens Road and strengthen and waterproof Bromley Street and Oldham Road bridges.

Over 3000m of track was upgraded and track remodelled between Manchester Victoria and Stalybridge. 17 new signals were also installed.

Further work takes place as planned on Sunday 22 August, Sundays throughout September and the weekend of 2 and 3 October, to make the final changes with less disruption to passengers.

All TransPennine Express (TPE) services will again be diverted into Manchester Piccadilly, with TPE services between Manchester Piccadilly and Liverpool being operated by rail replacement buses on Sundays. Buses will also replace Northern services between Stalybridge and Manchester Victoria calling at Ashton-under-Lyne.

This work is essential to enable more trains and faster trains to run in future. The newly renovated bridges now allow increased weight loading of more trains and the new and remodelled track will allow trains to run at faster speeds.

This milestone is a crucial part of the multi-billion-pound Transpennine Route Upgrade. This major railway upgrade programme will improve connectivity in the North of England by providing faster, more reliable services for passengers travelling between Manchester, Huddersfield, Leeds and York.

Neil Holm, Transpennine Route Upgrade Director for Network Rail, said: “We’ve made major progress across Greater Manchester on this key part of the Transpennine Route Upgrade. Our teams have worked around the clock over the past 16 days to improve journeys for passengers.

“As well as bringing more reliable services, this complex upgrade will eventually allow more trains and faster trains to run on the busy route between Manchester and York.

“We carefully planned the work to keep passengers moving during the upgrade. I want to say a big thank you to passengers for their patience while the improvements took place.”