Final phase of work for the new A556 Knutsford to Bowdon dual carriageway to start next next month.

Drivers will shortly be able to use the new £192 million A556 Knutsford to Bowdon dual carriageway in Cheshire, with the final phase of work starting next month.
Highways England, which is building the new link road between junction 19 of the M6 at Knutsford and junction 7 of the M56 at Bowdon, today detailed the final phase of road works for the project – paving the way for the new road to open in March , providing a faster and more reliable link between the two motorways.

Full weekend closures – of the existing A556, junction 19 of the M6 and junctions 7 and 8 of the M56 – are needed and are scheduled to start in mid-February.

The closures will allow the old road to be sealed off from through traffic and the motorway junctions to be tied into the new dual carriageway.
Highways England project manager Paul Hampson said:
“We are on course to open the new dual carriageway by the end of March, if not sooner. As well as starting work next month to connect the new dual carriageway to the M6 and M56 link roads, we’ll be using the weekend closures to do some preparation along the existing A556 which will become a B road with much-improved facilities for pedestrians and cyclists.”

Drivers are being advised the schedule for the final phase of work is dependent on the weather. The schedule currently involves:
a full weekend closure of the existing A556 and associated M6 and M56 junctions between 9pm on Friday 17 February and 5am on Monday 20 February
a full weekend closure of the existing A556 and associated M6 and M56 junctions from 9pm on Friday 3 March to 5am on Monday 6 March – with the new road opening to drivers that morning for the first time
a final full weekend closure of the old A556 and new A556 between 9pm on Friday 10 March and 5am on Monday 13 March to finalise work to seal off the old road

 